The National Perspective Plan (NPP) was prepared by the then Ministry of Irrigation (now Ministry of Jal Shakti) in August 1980 for water resources development through inter basin transfer of water, for transferring water from water surplus basins to water-deficit basins. 

Under the NPP, the National Water Development Agency (NWDA) has identified 30 links (16 under Peninsular Component & 14 under Himalayan Component) for preparation of Feasibility Reports. Details and status of the proposals for inter-state linking of rivers under the Inter Linking of Rivers Programme is furnished at Annexure.

The implementation of the ILR projects depend on the consensus of the concerned States. Thus the interlinking of rivers programme is being pursued based on the principle of consensus and agreement among the concerned States. An interlinking project would reach the implementation stage once agreement amongst party states is reached on water sharing. Thereafter for implementation all requisite statutory clearances need to be obtained.

Government of Uttar Pradesh has requested NWDA to take up the study of linking Sharda River to Gomtiriver. Draft Pre-Feasibility Report of the Intra State link viz; Sharda-Gomti link has been completed by NWDA  and submitted to the State Government in October, 2021.

This Information was given by the Minister of State for Jal Shakti, Shri Bishweswar Tudu in a written  reply in Lok Sabha today.

S.

No

Name

Rivers

States concerned

Status

Peninsular Component

 

 

 

1(a)

Mahanadi (Manibhadra)–

Godavari (Dowlaiswaram) link

Mahanadiand Godavari

Jharkhand, Madhya Pradesh, Chhattisgarh, Telangana,

Andhra Pradesh, Odisha, Karnataka and Maharashtra

FR Completed.

1(b)

Mahanadi (Bermul)–

Godavari (Dowlaiswaram) link

Mahanadi and Godavari

do

FR Completed.*

Preparation of DPR under progress.

2

Godavari(Inchampall)-Krishna(Pulichintala)

link

Godavariand Krishna

Odisha, Madhya Pradesh, Chhattisgarh, Telangana, Andhra Pradesh, Maharashtra

and Karnataka

FR Completed.

3

Godavari(Inchampalli)-Krishna (Nagarjunasagar) link

Godavariand Krishna

--do--

FR Completed.

DPR

Completed.

4

Godavari(Polavaram)

- Krishna(Vijayawada) link

Godavari and Krishna

--do--

FR Completed.

5

Krishna(Almatti)

–Pennar link

Krishna and Pennar

Telangana, Andhra Pradesh,Maharashtra and Karnataka

FR Completed.

6

Krishna (Srisailam)–Pennar link

Krishna and Pennar

--do--

FR Completed.

7

Krishna(Nagarjunasagar)-Pennar (Somasila) link

Krishna and Pennar

--do--

FR Completed.

DPR Completed.

8

Pennar (Somasila)–Cauvery(Grand Anicut) link

Pennar and Cauvery

Andhra Pradesh, Karnataka, Tamil Nadu, Kerala and Puducherry

FR Completed.

DPR Completed.

9

Cauvery (Kattalai)–Vaigai–Gundar link

Cauvery, Vaigai and

Gundar

Karnataka, Tamil Nadu, Kerala and Puducherry

DPR Completed.

10

Ken–Betwa link

Ken and Betwa

Uttar Pradesh and Madhya Pradesh

DPR (Phase – I, II & Comprehensive report) Completed.

Contd…

11

(i)

Parbati – Kalisindh –Chambal link

Parbati, Kalisindhand Chambal

Madhya Pradesh,Uttar Pradesh and Rajasthan requested to be Consulted during consensus building)

FR Completed.

(ii)

Parbati-Kuno-Sindh link

Parbati, Kuno and Sindh

Madhya Pradesh and Rajasthan

PFR completed.$

12

Par-Tapi-Narmada link

Par, Tapi and Narmada

Maharashtra and Gujarat

DPR Completed.
 

13

Damanganga – Pinjal link

Damanganga and Pinjal

--do--

DPR Completed.
 

14

Bedti-Varada link

Bedti and Varada

Maharashtra, Andhra Pradesh and Karnataka

PFR Completed.

Draft DPR completed

15

Netravati – Hemavati link

Netravati

and Hemavati

Karnataka, Tamil Nadu and Kerala

PFR Completed.

16

Pamba - Achankovil –Vaippar link

Pamba,Achankovil and Vaippar

Kerala and Tamil Nadu

FR Completed.

 

$ Integration of Eastern Rajasthan Canal Project of Rajasthan and Parbati – Kalisindh – Chambal link.